Lance Harold Standridge 45300 Essex Lane Lancaster, California 93534-1365
Granite Construction Company July 1986 to October 2009
Spring 2006- Fall 2009 Office Engineer- estimating staff Train new engineers, assistant to chief estimator, deliver and control bid documents, keep statistics on bidding process, Act as Construction DBE Liaison Officer; generate DBE participation and reporting forms; monitor consultant and contractor DBE compliance throughout projects; participate in DBE outreach efforts; estimate construction materials quantities for bids, write and administer storm water protection plans, inspect projects for safety program requirements, preform special projects for area manager
Spring 2006- Granite Construction Palmdale CA. Area Quality Control Supervisor Spring 2003 Radiation Officer Write and administer Quality Control Programs for projects and construction material manufacturing plants.
Summer 2000- Army Corp of Engineers - IDIQ Edward AFB, CA Project Mgr. Assistant / Field Spring 2003 Engineer.
1. Maintain files of: a.Transmittals, and an up to date register b.Submittals c.Project Schedule d.Daily Reports e.RFIs f.DCNs 1.Report and communicate daily w/COE Project Staff 2.Write Subcontracts and Purchase Orders 3.Submit monthly quantities and pay request 4.Write and approve all subcontractor monthly pay requests 5.Maintain Project Schedule 6.Write Quality Control Plan 7.Approve all Purchase Orders
Summer 1999- Army Corp of Engineers Plant 42, Palmdale, CA; Repair Runway and install lighting Summer 2000 Approx. 7000LF of runway and 4000 LF of adjacent Taxiways. Pulverize Runway and replace it w/recycled AB. AC paving shoulders. $8,000,000 No days out of conformance for the AC. CQC Mgr. / Project Engineer
1.Write QC Plan 2.Maintain files of: a.Transmittals, and an up to date register b.Submittals c.Daily Reports d.RFIs e.DCNs f.AS-builds. 3.Inspect and delegate inspect and testing the proper person of outside labs 4.Report and communicate daily w/ COE Project Staff 5.Submit daily CQC Reports
Spring 1999- Caltrans HWY 128 Santa Clarita, CA; Reconstruct 10 Miles on HWY 128, Summer 1999 $25,000,000 No days out of conformance for the AC. 105% Bonus CQC Manager
1)Maintain files of: a)Transmittals, and an up to date register b)Submittals c)Daily Reports d)RFIs e)DCNs f)AS-builds. 2)Report and communicate daily w/Caltrans Project Staff 3)Supervised 3 Techs for field and plant testing 4)Scheduled onsite lab for: a)Earthwork Testing b)Crushed Aggregate Base Testing c)AC testing.
Summer1998- LA County Public Works General William Fox Airfield Runway Runway and Taxi Spring 1999 Extension, w/ New Lighting. COE Marshall Mix. AC Bonus $17,000; P401 Mix CQC Manager/Project Engineer
1)Maintain files of: a)Transmittals, and an up to date register b)Submittals c)Daily Reports d)RFIs e)DCNs f)AS-builds. 2)Report and communicate daily w/LACPW Project Staff 3)Maintain Project Schedule 4)Write Quality Control Plan 5)Supervised 3 Techs for field and plant testing 6)Scheduled onsite lab for: a)Earthwork Testing b)Crushed Aggregate Base Testing c)AC testing
Spring 1997 Army Corp of Engineers Plant 42, Palmdale, CA; Repair Runway and install lighting Summer 1998 approximately 5,000 LF of runway. Lighting, removing AC overly, and replacing it W/ PCCP, AC paving shoulders. $16,000,000 CQC Manager
1.Write QC Plan 2.Maintain files of: 3.Transmittals, and an up to date register 4.Submittals 5.Daily Reports 6.RFIs 7.DCNs 8.AS-builds. 9.Inspect and delegate inspect and testing the proper person of outside labs 10.Report and communicate daily w/ COE Project Staff 11.Submit daily CQC Reports
Winter 1996 I-10 Frontage Roads Tucson, ADOT, $18,000,000 Project; End Product AC paving under PCC paving areas. Project Received 105%Bonus for AC Material and Compaction. QC Mgr.
1.Maintain files of: a.Transmittals, and an up to date register b.Submittals c.Daily Reports d.RFIs e.DCNs f.AS-builds. 2.Report and communicate daily w/ADOT Project Staff 3.Write Subcontracts and Purchase Orders 4.Submit monthly quantities and pay request 5.Write and approve all subcontractor monthly pay requests 6.Maintain Project Schedule 7.Write Quality Control Plan 8.Approve all Purchase Orders 9.Supervised 3 Granite Techs for field and plant testing 10.Scheduled onsite lab Techs for: a.Outside Crushing, fractured face, sieve b.Earthwork c.Base materials d.AC testing
Spring 1996 - U.S. Department of Transportation FHWA; Mt Lemon HWY Phase IV. Re-Align 7 Summer 1997 Miles of Mt. Road W/ Mechanically Stabilized Embankment Walls and Bridge.
1.CQC Mgr. for all Phases of work: a.Rock Blasting b.Onsite Material Screening c.Earthwork, and Base Materials d.Bridge and other Concrete Structures e.AC Paving 2.Maintain files of: a.Transmittals, and an up to date register b.Submittals c.Daily Reports d.RFIs e.DCNs f.AS-builds. 3.Report and communicate daily w/FHWA Project Staff 4.Schedule Testing for all material sampling and testing: a.Compaction tests of earthwork, structural backfill, and base placement b. Concrete sampling, air content, slump, cylinders, and adjusting add mixtures c.AC Testing Plate Sampling, Compaction Monitoring w/ Nuc. Core 5.Maintain Daily Spread lot Records - Project Received 105%Bonus for AC Material and Compaction. 6.Write QC Plan
Summer 1995 - Nogales Pit Plant Engineer Establish out side sales and provide materials for ADOT Spring 1996 Road Contract w/ 6 miles of 5-lane road. AB and AC w/ bonus of 104.8% for AB conformance and 104.0% Bonus for AC Material conformance and Compaction. CQC Manager / Plant Engineer
1.Maintain files of: a.Transmittals, and an up to date register b.Submittals c.Daily Reports d.RFIs e.DCNs 2.Report and communicate daily w/Branch Project Staff 3.Write Subcontracts and Purchase Orders 4.Submit monthly quantities and pay request 5.Write and approve all subcontractor monthly pay requests 6.Maintain Plant Schedule 7.Write Quality Control Plans 8.Approve all Purchase Orders 9.Supervised 3 Granite Techs for field and plant testing 10.Scheduled Techs for: Earthwork, Plant produce, Concrete, and AC testing
Spring 1995- Sonoita HWY, AZ, ADOT, 18 Miles, End Product Overlay w/ Portable Plants Summer 1996 Quality Control /Project Engineer
1.Conducted field-testing:: a.AC Testing Plate Sampling, Compaction Monitoring w/ troxler compaction gauge, core AC 2.Maintain Daily Spread lot Records - Project Received 104.8%Bonus for AC Material and Compaction 3.Review all plans and maintain up to date changes for as AS-builds. 4.Maintain files of: a.Transmittals, and an up to date register b.Submittals c.Daily Reports d.RFIs e.DCNs 5.Report and communicate daily w/ADOT Project Staff 6.Write Subcontracts and Purchase Orders 7.Submit monthly quantities and pay request 8.Write and approve all subcontractor monthly pay requests 9.Approve all Purchase Orders
Winter 1994- Saffard, AZ, ADOT, Storm Drain, and Detention Basin, Shoulder Widening, w/ New Spring 1995 Sidewalks, 4.5 Mile, $6,500,000 Project Engineer
1.Write QC Plan 2.Maintain files of: a.Transmittals, and an up to date register b.Submittals c.Project Schedule d.Daily Reports e.RFIs f.DCNs 3.Write Subcontracts and Purchase Orders 4.Submit monthly quantities and pay request 5.Write and approve all subcontractor monthly pay requests 6.Approve all Purchase Orders
Fall 1994 Tomato Plant Parking Lot North of Wilcox, AZ $95,000 Design, PM, and Survey. Project used as a test area for the Cement Treated SG, and AC for the Project listed below.
1.Supervised 3 Granite Techs for field and plant testing 2.Scheduled onsite lab for: a.Outside Crushing, fractured face, sieve b.Earthwork c.AC testing 3.Write and approve all subcontractor monthly pay requests 4.Approve all Purchase Orders 5.Write QC Plan 6.Maintain Project Schedule 7.Report and communicate daily w/ Project Staff
Summer 1994- North of Wilcox, AZ, County Road Improvements Administrated By ADOT; 7 Mile Winter 1994 New Road Alignment with Cement Treated SG, and End Product AC. CQC Manager / Project Engineer
1.Supervised 3 Granite Tech.s for field and plant testing 2.Scheduled onsite lab for: c.Outside Crushing, fractured face, sieve d.Earthwork e.AC testing 3.Write QC Plan 4.Report and communicate daily w/ADOT Project Staff 5.Maintain Project Schedule
Summer 1994 Saffard HWY AZ. ADOT 11 Miles End Product Overlay w/ Portable Plants Quality Control / Field Engineer
1.Conducted field-testing:: a.AC Testing Plate Sampling, Compaction Monitoring w/ troxler compaction gauge, core AC 2.Maintain Daily Spread lot Records - Project Received 104.3%Bonus for AC Material and Compaction 3.Report and communicate daily w/ ADO Project Staff 4.Write QC Plan 5.Maintain Project Schedule
Fall 1993- San Simon Port of Entree I-10 New Mexico State Line 10 Miles of Milling and overlay Summer 1994 w/ New Weight Station and 2 new Rest Station Parking Areas w/ 15,000 CY PCCP, 25,000 TN AB, and 150,000 Tons AC End Product. Quality Control Mgr. and Field Tech. Recognized as Partner of the project. Project received the AGC National Excellence in Partnering Award.
1.Portable Crusher, Wash Plant, AC Plant, and Concrete Plant 2.PCCP Paving QC Tech.: Sampling, Air Content, Slump, Cylinders, adjusting add mixtures 3.Supervised 3 Granite Techs for field and plant testing. 4.Schedule Lab Testing or Conducted Field Testing 5.AC Testing Plate Sampling, Compaction Monitoring w/ troxler compaction gauge 6.Core AC 7.Maintain Daily Spread lot Records 8.Report and communicate daily w/ ADOT Project Staff 9.Write QC Plan
Summer 1993 Demming, NM, City Airport retrofit taxiways, and parking apron, $6,500,000; FAA P 401 Mix, QC MGR./ Project Asst. Mgr.
1.Scheduled onsite lab for: a.Outside Crushing, fractured face, sieve b.Earthwork c.AC testing 2.Supervised 3 Granite Techs for field and plant testing. 3.Write QC Plan 4.Report and communicate daily w/ NMDOT Project Staff 5.Review all plans and maintain up to date changes for as AS-builds. 6.Maintain files of: a.Transmittals, and an up to date register b.Submittals c.Daily Reports d.RFIs e.DCNs 7.Write Subcontracts and Purchase Orders 8.Submit monthly quantities and pay request 9.Write and approve all subcontractor monthly pay requests 10.Approve all Purchase Orders
Spring 1993 - Fort Bowie AZ ADOT 9 Miles of I-10 Mile and Overlay w/ Portable Plants, Summer 1993 and Bridge Retrofit $13,000,000 - Quality Control / Field Engineer
1.Schedule Lab testing or field-testing 2.AC Testing Plate Sampling, Compaction Monitoring w/ troxler compaction gauge Core AC 3.Report and communicate daily w/ ADOT Project Staff 4.Maintain Daily Spread lot Records - Project Received 104.3%Bonus for AC Material and Compaction 5.Write QC Plan 6.Maintain Project Schedule
Winter 1992 Nevada Branch Joint Venture Los Vegas, Nevada County Flood Control Project 3.5 Spring 1993 Mile of Channel Bank Protection w/ RCC and a Earth Fill Dam w/ RCC Cap on Top and Down Stream Face - $12,00,000 Phase 3 35,000 CY RCC - Quality Control Mgr. / Field Engineer 1.Write QC Plan 2.Schedule Lab Testing or Conducted Field Testing: a.Mix Design Supervise w/ out side lad b.Aggregate testing cold feed to Pug Mill w/ Moisture Check for Conformance c.Measure Thickness and Placement Temperatures 3.Monitor County Lab Concrete Testing Make Cylinders, Slump, Air, Temp 4.Report and communicate daily w/ Project Staff 5.Maintain Submittal Register 6.Maintain Project Schedule 7.Maintain files of: a.Transmittals, b.Submittals c.Daily Reports d.RFIs e.DCNs 8.Review all plans and maintain up to date changes for as AS-builds.
Fall 1992 - Robles Jct. Tucson AZ ADOT 12 Miles of New Road Alignment w/ 15 New Multi-barrel Box Culverts, and All End Product QC Testing - $14,000,000 - Quality Control Mgr. / Field Engineer Project Received 105%Bonus for AC Material and Compaction 1.Schedule Lab Testing or Conducted Field Testing a.Concrete Testing Make Cylinders, Slump, Air, and Temp. b.AC Testing Plate Sampling, Compaction Monitoring w/ Nuc., Core and Maintain Daily Spread lot Records 2.Write QC Plan 3.Review all plans and maintain up to date changes for as AS-builds. 4.Maintain file of all transmittals and an up to date register 5.Inspect and delegate inspect and testing the proper person of outside labs 6.Report and communicate daily w/ ADOT Project Staff 7.Submit daily CQC Reports
Summer 1992 - Lake Pleasant, PHX. AZ- Bureau of Reclamation - RCC DAM 15,500 CY; Dam Retrofit Quality Control Mgr. / Field Engineer 1.Review all Plans and maintain: a.RFIs b.DCNs c.As-builds d.Project Schedule 2.Review all Shop drawings: a.Formwork b.Embedded Material c.Concrete Plant Setup d.Nitrogen Injection System 3.Layout Concrete Plant and Conveyor Placement for Distribution System 4.Inspect and Sign off on Daily Placements Cards 5.Report and communicate daily w/Bureau Project Staff 6.Inspect Surface Cleanliness for Concrete Latents 7.Concrete Temp Max. Of 75 Degrees 8.Maintain - a.Aggregate Watering System b.Schedule Aggregate Delivery, and Measurer Stockpiles c.Bureau Daily Reports and Files 9.Write QC Plan
Summer1991 I-17 North Phoenix, AZ; ADOT- Rose Garden Traffic Interchange and Overpass. The first partnering project for both the AZ Branch and ADOT. $8,750,000 Recognized as Partner of the project. CQC Manager and Project Engineer
1.Review all Plans and maintain a.RFIs b.DCNs c.As-builds, and Project Schedule 2.Review all Shop Drawings a.Storm Drain System b.Bridge Form Work c.Crusher Set-up 3.Explore on site mining areas and designate crusher locations. 4.Conduct on site Earthwork, Base, Concrete, and AC field tests 5.Conducted weekly QC meetings w/ ADOT QA personal 6.Report and communicate daily w/ ADOT Project Staff 7.Schedule Techs to cover lab work. 8.Write QC Plan 9.Write Subcontracts and Purchase Orders 10.Submit monthly quantities and pay request 11.Write and approve all subcontractor monthly pay requests 12.Approve all Purchase Orders
Spring 1990- ASARCO Inc. Kearney AZ. Ray Mine Expansion $ 35,000,000 General Contractor Spring 1991 Bechtel Corp. of San Francisco; Structural Concrete +30,000 CY for a Copper Mine Concentrator and Overland Conveyor System w/ 280 TN Rock Truck Dump Pocket. Safety and Quality Control Manager on a 145 work force Project. 1.Review All Plans and Maintain registers and correspondence for RFIs, DCNs, and As-Builds. 2.Review All Shop Drawings for formwork, structural steel, electrical duck banks, and embedded Materials. 3.Maintain submittal log for concrete mix designs, all metal embedded materials (Bolts, Plates, and Beams) 4.Inspect for Conformance and Correct: a.Earthwork b.Rebar Placement c.Formwork d.Bolts, Embedded Materials Placement e.Finished Structures and Designate Repairs 5. Schedule Granite survey crews and concrete daily placement order for maximum efficacy. 6.Report and communicate daily w/Bechtel Project Staff 7.Calculate all excavation, backfill, and concrete quantities for payment and justification as needed. 8.Safety Engineer - Enforce all State, Federal, Bechtel, Corporate Safety Standards, and Mine safety codes. Conduct all safety meetings, and accident investigation logs. 9.Write QC Plan
Fall 1989- Globe, AZ Copper Mine RCC Dam for Acid Detention Basin, QC Engineer
1.QC Testing for pug mill plant Portable Lab sieve, moisture; order materials and measure stockpiles
Fall 1988- Patagonia Lake, AZ, ADOT New Road Construction 6.5 Miles, $8,000,000 Summer 1989 QC Manager for the portable Crusher making AB, and ended up becoming the Asst. Construction Mgr. 1.Testing AB: Sieve, PI, Measure Stock Piles; Concrete: slump, air, temp, cyl.s
Summer 1988 Nogales, AZ, ADOT, and Compound Curve multi barrel box culvert, Project Engineer
Summer 1988 Sonoita HWY, AZ, ADOT, Guardrail Project w/ box culvert extension, 9 Miles, Project Engineer
Spring 1988- AZ Branch Office Office Engineer Spring 1989 1.AGTEC, Pay Dirt, Take Off work 2.Bid quotation 3.Bid closing
Summer 1987 Bisbee AZ ADOT End Product AC Granite used an onsite AC Plant and paved over a savvier alligator road during monsoon season. Had plenty of compaction penalties but the estimate had them covered. 15 Miles of pavement overlay. QC Engineer
1.Conducted field-testing 2.AC Testing Plate Sampling, Compaction Monitoring w/ troxler compaction gauge 3.Core and Maintain Daily Spread lot Records
Winter 1986 Sells AZ ADOT First End Product Spec. Project for the AZ Branch Only one day out of compliance for 1 of 4 tests ran on gradation. At this time there were no Bonus only Penalties. 11 Miles of road. Field Tech
1.Conducted field-testing 2.AC Testing Plate Sampling, Compaction Monitoring w/ troxler compaction gauge 3.Core and Maintain Daily Spread lot Records
Summer 1986- Hughes Pit Tucson QC Tech. Tested all materials for the crushers, wash plant, and Spring 1988 two AC Plant (drum, and stack). Worked off and on to locate and survey the next Tucson Pit purchase w/ over 400 test holes w/ various equipment (Track Hoes to 4 Dia. Drilling Rigs). Produce mix design (AC, and Concrete) lab work and verification testing.
Fall 1985- Western Technologies Inc. Flagstaff, and Tucson Offices - Worked on several Summer 1986 earthwork, concrete, and AC projects as a OQ field technician.
Nation Institute for Certification in Engineering Technologies CT - #000642 through 11/01/2010
Spring 1985 Graduated from Northern Arizona University l Flagstaff, Arizona Civil Engineering Technology 3.10 GPA
While Attending Northern Arizona University Summer 1985 Spring 1982
Summers 1984- US Forest Service Juneau, Alaska Survey Crewmember in the outback country for 1983 future logging sales.
Winters 1984- Arizona Snowbowl Ski Resort Flagstaff, Arizona - Ski Patrol, and Maintenance. 1983-1982
Winters 1984- Museum Club Bar Flagstaff, Arizona Door Man, and Bouncer 1983-1982
Summer 1981- US Forest Service Flagstaff, Arizona Flagstaff Hotshots Crewmember, and lead 1980-1979 sawyer Winter 1981- Construction Mason and Laborer for various contractors in Southeastern Arizona 1980-1979- Summer 1978
Summer 1978- Central Arizona College Casa Grande, Arizona Pre-Engineering Studies, Track Team Summer 1976 Scholarship Javelin - Dormitory Resident Assistant
Spring 1976 Graduated from Buena High School Sierra Vista, Arizona 3.15 GPA
Memberships: National Institute for Certification in Engineering Technologies ASTM International Member American Society of Civil Engineers AGC International
Completion of the following courses: Suretrak Project Scheduling Class, 08/22/06 Storm Water Pollution Prevention Plans for Construction Activities 06/28/05 AutoCAD Level-1 Fall 2003 Traffic Control Coning & Flagging 11/19/03 Caltrans Quality Control Manager School 02/15/03 Radiation Control Officer Training 03/05/02 Excel Training Level-2 04/01/05 COE Quality Control Manager School 04/15/97 AGC Supervisors Management Class 05/14/95 Hot Plant Smoke School and Reading Test 04/15/94 Troxler Gauge Operation Class 07/20/86
References supplied upon request.
|